Summer getaway drivers forced to abandon new £1M charging points at service station after electricians fail to hook them up to power supply

Summer getaway drivers have been forced to abandon new £1million charging points at a service station after electricians failed to hook them up to the power supply. 

The bank of 16 Tesla superchargers – which cost £1million to install – were not connected because the grid was not ready to cope with the demand. 

Ken McMeikan, chief executive of Moto – that operates the Pease Pottage site near Gatwick – said the power was meant to be turned on at the start of July but will now be delayed until September 9, according to The Sunday Times

The charging points are in seriously high demand – with 400,000 EV drivers set to be travelling around Britain this weekend alone. 

Mr McMeikan said: ‘It will get worse before it gets better.

Summer getaway drivers have been forced to abandon new £1million charging points at a service station after electricians failed to hook them up to the power supply

Summer getaway drivers have been forced to abandon new £1million charging points at a service station after electricians failed to hook them up to the power supply

The bank of 16 Tesla superchargers - which cost £1million to install - were not connected because the grid was not ready to cope with the demand

The bank of 16 Tesla superchargers – which cost £1million to install – were not connected because the grid was not ready to cope with the demand

‘People keep talking about the number of chargers, but I keep talking about the amount of power that is available to actually turn those chargers on.’ 

It comes after 24 Gridserve and 24 Tesla chargers at Medway services in Kent were supposed to be operational in May, but the power will not be turned on until December.   

Meanwhile projects have been postponed at Birch, near Rochdale, and at Lancaster services due to deadline for preparation work being missed. 

Near Exeter Moto wanted a service station to have 56 chargers for this weekend but has ended up with 33. 

Mr McMeikan said: ‘If you think about the amount of fuel we supply through petrol forecourts that we are replacing with electricity, I genuinely don’t think that the grid and the regional operators have really understood how much electricity is required and how quickly.’ 

The charging points are in seriously high demand - with 400,000 EV drivers set to be travelling around Britain this weekend alone

The charging points are in seriously high demand – with 400,000 EV drivers set to be travelling around Britain this weekend alone

In a bid to help the issue Mr McMeikan now hopes to develop solar farms on land adjoining twelve motorway service stations, in locations such as Reading and Wetherby. 

A spokesperson for UK Power Networks told The Sunday Times: ‘In order to complete the works a number of consents are required, and we are working with the relevant statutory authorities and other parties to ensure the works are completed as soon as possible.’ 

MailOnline has contacted UK Power Networks for comment. 

DailyMail

Leave a Reply

Your email address will not be published. Required fields are marked *

You May Also Like

CNN removes Don Lemon’s name from This Morning

‘We want to keep the focus on the news’: CNN removes Don…

Daylight ‘robbery’ horror as woman in her 60s is stabbed to death by thief who ‘tried to steal her bag’ as she waited for a bus: Police arrest man, 22, on suspicion of murder

A woman in her 60s was allegedly stabbed to death by a…

Murdaugh claims ‘vile’ social media comments drove someone to seek revenge for boat wreck

Alex Murdaugh today broke down in tears as the prosecutor ended his…

Ed Sheeran gives away Chicago-style hot dogs to fans at stand known for ‘insulting their customers’ just HOURS before his concert at Soldier Field

Ed Sheeran gave some lucky fans the surprise of a lifetime after…